Energy Transition Now

Decarbonization • Electrification • Grid Modernization • Renewables and EVs

A $6B nuclear startup faces a hostile NIMBY crowd and a fight with its own VC

A Sequoia-led round made Valar one of nuclear’s richest startups. Now residents near Price, Utah are pushing back on Project Beehive, and Valar is suing an early backer whose founder carries Epstein-file baggage.

Nuclear 101: What Is a High-Temperature Gas Reactor?Image:DOE

Valar Atomics, the $6 billion standard-bearer of the alleged U.S. nuclear renaissance, is running into pushback from the Utah community where it wants to build a slew of microreactors — and some legal pain from its enormous Sequoia-led VC fundraise.

Valar has raised $1 billion on the strength of one test reactor and an unprecedented societal license to build small reactors, although not in Carbon County. More than 100 people packed an overflow meeting of the county’s Planning Commission in Price, Utah, on Oct. 6 to hear CEO Isaiah Taylor pitch a fleet of tiny advanced reactors on 640 acres of state trust land. “We don’t want you here!” one attendee yelled as the Valar team introduced itself, KUTV reported. Taylor tried to entice the crowd with jobs and offered an out: “If the community doesn’t want us here, we won’t do it.” The room applauded. 

Valar, founded in 2023 and based in El Segundo, California, is one of dozens of VC- and billionaire-funded fission startups intent on reversing the decline of America’s nuclear fleet and powering our AI-data-centers-in-space future. Its unlicensed high-temperature gas reactors are cooled by helium and powered by TRISO, a fuel that is costly, made only at pilot scale, and, in Valar’s case, dependent on scarce high-assay low-enriched uranium. Valar’s thesis is to build one 25-megawatt design, which so far exists only on paper, thousands of times. Backers include Anduril founder Palmer Luckey, Palantir’s Shyam Sankar, Lockheed Martin, Day One Ventures, and Sequoia, whose partner, Shaun Maguire, now sits on Valar’s board. Early investor Day One is now Valar’s adversary in Delaware court.

Conventional nuclear reactors are enormous civil engineering projects that produce in the neighborhood of 1,000 megawatts, enough to power hundreds of thousands of homes. They are also notoriously expensive, over budget, and difficult to build. In the past 30 years, the U.S. has brought just three new reactors online: Watts Bar 2 in 2016, 43 years after construction began, and Vogtle Units 3 and 4 in 2023 and 2024, which came in years late and at more than double their original budget. Valar’s premise is that shrinking the reactor and modularizing production will make building a nuclear plant less like a cathedral and more like a factory. The result, in theory: economies of mass production that make nuclear power too cheap to meter.

Skeptics argue that small modular reactors, or SMRs, are an engineering solution for what is fundamentally a financial problem. Nuclear has historically gotten cheaper by getting bigger, and small reactors sacrifice that advantage. The International Energy Agency’s 2025 analysis assumes a first-of-a-kind SMR costs roughly double an efficiently built large reactor in overnight capital cost. And every small reactor still needs the pumps, piping, controls, and balance-of-plant that make nuclear hard to build in the first place. NuScale, the first SMR design approved by the NRC, lost its flagship project with Utah Associated Municipal Power Systems in 2023 as costs climbed.

Taylor’s answer is that the reactor is not the problem. “Most of the cost of nuclear is not the reactor itself — it’s the site,” he told Deep Tech Field Notes. Valar’s plan is to cluster hundreds of identical units on a single “gigasite” and spread those site costs across all of them. It’s an argument good enough to raise $1 billion.

Valar’s “Project Beehive” spreads over more than 9,000 acres of state trust land and BLM land near Price, with plans to deploy 456 microreactors powering AI data centers, according to documents obtained by NPR. That’s 9.6 gigawatts, more than double Utah’s average generation. At the Price meeting, Valar presented about 200 reactors on the state parcel, Fox13 reported.

About $130 billion in data center projects were blocked or delayed by local opposition in the first quarter of 2026 alone, and opposition groups are now active in 49 states. Say what you want about AI data centers, but utility-scale solar farms and transmission projects are getting swept up in the same NIMBYism, lumped together and opposed as one thing. Big projects have become a proxy for techno-broligarchs and outside control. In Price, residents weren’t even given a voice at the meeting.

Valar also has a money fight on its hands. Day One Ventures put $1 million into Valar’s seed round and $15 million into its Series A, leaving it with less than 5% of the company, according to a letter Taylor posted on X on Oct. 9. When Sequoia, the 800-pound gorilla of venture capital, came calling, Valar asked earlier investors to waive their pro rata rights. Every other major investor agreed to sit out the round, Taylor wrote, but Day One insisted on its “spring back” right to participate. The day before closing, a majority of investors amended the rights agreement to delete spring back altogether. Taylor says Day One then hired notoriously litigious law firm Quinn Emanuel; Valar sued for declaratory relief in Delaware. Hours after Taylor’s post, Day One founder Masha Bucher, a former Jeffrey Epstein publicist and former member of Nashi, a pro-Putin youth group, published her own account, writing that four of six major investors joined the Series B without waiving their rights and that Day One offered to give up most of its allocation. “Valar signed a contract, violated that contract, and is now suing us,” she wrote on X, adding that Day One has no interest in suing. Bucher also alleged that Taylor made a significant secondary share sale from which Day One was excluded.

Internecine boardroom struggles like this are common. Early investors typically give up their pro rata rights when a big gorilla funds a later round; that’s just VC math when dealing with big rounds and egos. These fights rarely make it into public view, let alone Delaware court. But here we are.

Taylor told Carbon County that if the community didn’t want Valar, Valar wouldn’t come. A packed room in Price gave him an answer.